Finance:Invitation to tender

From HandWiki
(Redirected from Finance:Invitation for bid)
Short description: Business process
A tender announcement from the Indonesian Ministry of Finance

An invitation to tender (ITT, otherwise known as a call for bids[1] or a request for tenders) is a formal, structured procedure for generating competing offers from different potential suppliers or contractors looking to obtain an award of business activity in works, supply, or service contracts, often from companies who have been previously assessed for suitability by means of a supplier questionnaire (SQ) or pre-qualification questionnaire (PQQ).

The term "notice inviting tenders" (NIT) is often used in purchasing in India.[2] The European Union's institutions often use the term "calls" in reference to tendering procedures, covering both "calls for tenders" and "calls for expressions of interest for the award of supply, service and works contracts".[3]

An ITT differs from a request for quotation (RFQ) or a request for proposal (RFP), in which case other reasons (technology used, quality) might cause or allow choice of the second-best offer. An RFP is a request for a price from a supplier, but the buyer would also expect suggestions and ideas on how the project work should be done. RFPs are thus focused on more than just pricing/cost, they entail some consultation with the contractor or vendor. The closest equivalent to an ITT in the mainstream private sector is an RFP which, since public money is not involved, typically has a less rigid structure.

Typology

  • Open tenders, open calls for tenders, or advertised tenders are open to all vendors or contractors who can guarantee performance.
  • Restricted tenders, restricted calls for tenders, or invited tenders are only open to selected pre-qualified vendors or contractors. The tender stage may form part of a two-stage process, the first stage of which (as in the expression-of-interest (EOI) tender call) was itself advertised,[4][5] resulting in a shortlist of selected suitable vendors. The reasons for using restricted tenders differ in scope and purpose. Restricted tenders can come about because of:
    • confidentiality issues (such as in military contracts)
    • the need for expeditiousness (as in emergency situations)
    • a need to exclude tenderers who do not have the financial or technical capabilities to fulfill the requirements.
  • Sole source tenders, where only one potential supplier is invited to submit a tender. A sole source tender may be used where there is essentially only one suitable supplier of the services or product.

Etymology

Dictionaries explain the etymology as coming from Old French tendre, which means 'to offer'.[6]

Typical template contents

A typical invitation to tender template in any project has the following sections:[7]

  • Introduction
  • Project background
  • Legal issues: proposed terms and conditions of contract
  • Supplier response required
  • Timetable for choosing a supplier
  • Requirements for tender submission, for example a fully completed but otherwise unamended form of tender must be submitted by the specified deadline.

Variants may be requested in an invitation to tender and accepted for evaluation alongside fully compliant tenders. Variants allow suppliers to offer proposals which differ in non-essential terms from the supplies or services requested. Invitations which specify that variants will be accepted may reflect buyers' uncertainty about the best way of meeting their needs, even after pre-tender consultation with suppliers. The European Commission has suggested that requesting variants is one way in which suppliers can be asked to offer more socially responsible solutions to meeting public needs.[8]

Locating tender opportunities

Public sector organisations in many countries are legally obliged to release tenders for works and services. In the majority of cases, these are listed on their websites and traditional print media. Electronic procurement and tendering systems or e-procurement are also increasingly prevalent. The European Union states that 235,000 calls for tender are issued annually using its Tenders Electronic Daily (TED) system, including those issued by countries in the European Economic Area and beyond.[9] Public sector organisations in the United Kingdom use this system but from 11 pm on 31 December 2020, at the end of the Brexit transition period, a new e-notification service called "Find a Tender" (FTS) began to be used to post and view public sector procurement notices.[10] Relevant new procurement opportunities launched after 11 pm on 31 December 2020 must be published on this website.[11]

A number of companies provide subscription alert services which send notifications of relevant tender documents to the subscriber.

An array of private organisations also assist businesses in finding out about these tenders. Cost may vary from a few pounds a week to a few hundred.

Because of the specialised language and sometimes difficult-to-grasp procedures, there are several consulting organizations, who offer companies tender writing training, or undertake bid-writing for them.[citation needed]

ITTs may be distributed to potential bidders through a tender service, allowing businesses to receive and search live tenders from a range of public and private sources. These alerts are most commonly sent daily and can be filtered down by geographical area, or by business sector.[citation needed] Some tendering services divide types of business opportunities very finely in their own way, by CPV (Common Procurement Vocabulary) codes.[12] This enables a business to find ITTs specific to what that business can supply.[citation needed]

An ITT is usually an open invitation for suppliers to respond to a defined need as opposed to a request being sent to selected potential suppliers. The ITT often requests information following on from other information gathered previously from responses to a Request for information (RFI). This will usually not only cover product and service requirements, but will also ask for information about the suitability of the business.[13] A supplier questionnaire or pre-qualification questionnaire may be used to elicit suitability information from suppliers in a consistent manner.

An ITT is usually expected to conform to some legally standardized structure designed to ensure impartiality,[citation needed] and the tender bid winner is entitled to take responsibility of the contract business supply documentations formalities and settle any tender bid engagement charges for official recording.[citation needed]

Pre-qualification questionnaires

Supplier questionnaires or pre-qualification questionnaires (PQQs) ensure that potential suppliers are all asked the same information when assessing their suitability to be invited to tender or to have their tenders evaluated. Some organisations issue a standard pre-qualification questionnaire, for example the UK government has developed standard core PQQ questions which have been revised several times and are "mandated for use" across government, and has also stipulated that PQQs should not be used by central government contracting bodies when procuring goods or services valued less than the threshold values set by European and UK procurement legislation.[14]

Tender box

A tender box is a mailbox used to receive the physical tender or bid documents, or a digital equivalent.[15] When a tender or bid is being called, a tender or bid number is usually issued as a reference number for the tender box. The tender box would be open for interested parties to submit their proposals for the duration of the bid or tender. After the closing date, the tender box is closed and sealed and can only be opened by either the tender or bid evaluation committee or a member of the procurement department with two witnesses.

Even though the tender box is not implemented in every country around the world, the procedure remains the same. Tenders have a bidding period available to prepare and bid. Research has shown that the length of this period might affect the number of bids and as a result competition among renderers [16]

Double envelope system

In an open bid or tender system, a double envelope system may be used. A double envelope system separates the technical proposal (based on and intended to meet the statement of work) from the financing or cost proposal in the form of two separate and sealed envelopes. During the tender evaluation, the technical proposal would be opened and evaluated first followed by the financing proposal. The objective of this system is to ensure a fair evaluation of the proposal. The technical proposal would be evaluated purely on its technical merits and its ability to meet the requirements set forth in the Invitation without being unduly skewed by the financial proposal.

Security deposit

Registered contractors may be required to furnish a bond for a stipulated sum as security or earnest money deposit to be adjusted against work done, normally in the form of bank guarantee or surety.

Tender validity date

A tender validity date is a date until which a tenderer commits to keeping their prices (and other tender details) open for acceptance (or otherwise) by the client. Such a date is usually included in a form of tender,[17] either as a specified date or as the termination of a specified period from another key tender date. For example, in tendering for gym equipment in 2013, West Dunbartonshire Council required tenderers to accept that "Your tender shall remain open for acceptance for ninety (90) days from the date for return of tenders indicated above, or any subsequent date notified to you by us. Your tender may be accepted by us at any time during this period."

Post-tender negotiation

Post-tender negotiation involves negotiation between an intending buyer and seller after a seller's tender has been submitted. An initial stage may involve tender clarification, which is intended to eliminate any uncertainties or contradictory elements of a proposal, before moving into a true "negotiation" phase.

The Chartered Institute of Procurement & Supply believes that "provided it is undertaken professionally and ethically, ... post tender negotiation is an appropriate process to secure value for money.[18]

Related proposal types

Other types of proposal and terms in use include:

See also

References

  1. Consular reports: Commerce, manufactures, etc, Issues 164-167. United States. Bureau of Foreign Commerce, United States. Dept. of Commerce and Labor G.P.O., 1894. Pg 361
  2. Telecommunications Consultants India Limited, Notice Inviting Tenders (NIT), accessed 6 March 2019
  3. Council of the EU, Procurement at the General Secretariat, last reviewed on 25 October 2022, accessed 9 May 2023, reproduction authorised provided that the Council of the EU is always acknowledged as the original source of the material.
  4. Urizar, Mark (24 July 2013). The Project Manager's Checklist for Building Projects: Delivery Strategies & Processes. Xlibris Corporation (published 2013). p. 236. ISBN 9781483662954. https://books.google.com/books?id=EWmLAAAAQBAJ. Retrieved 2015-12-03. "The Expression of Interest (EOI) tender call is to inform tenderers of the context of the project, nature of proposed appointment and submission requirements. The aim of the EOI process is to shortlist the contenders who may be suitable for the appointment." 
  5. Compare: Herbst, Douglas; Edmondson, Samuel A. (2012). "Design-Build Procurement Approaches". in Shorney-Darby, Holly. Design-build for Water and Wastewater Projects. American Water Works Association. p. 73. ISBN 9781583218181. https://books.google.com/books?id=kiUG3w0KGmkC. Retrieved 2015-12-03. "An Expression of Interest (EOI) is a document that an owner can issue prior to the release of the RFQ or RFP. [...] An EOI [...] would request basic information about the design-builder, solicit comments on the requested project features, and ask for an EOI for the project from the practitioners." 
  6. TheFreeDictionary by Farlex, Tender, accessed 4 June 2020
  7. Lasa Information Systems Team (10 September 2007). "Invitation to tender". PM Hut. http://www.pmhut.com/project-management-invitation-to-tender. 
  8. European Commission, Directorate-General for Employment, Social Affairs and Inclusion and Directorate-General for the Internal Market and Services, Buying Social: a Guide to Taking Account of Social Considerations in Public Procurement, Publications Office, 2011, accessed 30 May 2023, pages 30-31
  9. European Union, TED: Tenders Electronic Daily, accessed 13 June 2020
  10. Cabinet Office, Public-sector procurement from 1 January 2021, published 24 April 2020, accessed 13 June 2020
  11. Cabinet Office, Annexe A: Frequently asked Questions: End of Transition Period (TP), published 10 December 2020, accessed 26 December 2020
  12. "Global Tenders: International Tenders, Government Tender Portal" (in en). https://www.biddetail.com/. 
  13. Mhay, S. and Coburn, C., Meaning of RFQ RFI RFT RFP, Negotiation Experts, accessed 5 August 2021
  14. Crown Commercial Service, Procurement Policy Note – Use of Pre-Qualification Questionnaires: Action Note 01/12 10 February 2012, accessed 5 August 2021
  15. Electronics Corporation of India Limited, User Manual - Tender Box Opening, Version 2.0, accessed 5 August 2021
  16. Pliatsidis, Andreas Christos (2022-11-01). "Impact of the time limits for the receipt of tenders on the number of bidders: evidence from public procurement in Greece". Journal of Public Procurement 22 (4): 314–335. doi:10.1108/JOPP-05-2022-0025. ISSN 2150-6930. https://doi.org/10.1108/JOPP-05-2022-0025. 
  17. Form of tender, accessed 1 June 2020
  18. CIPS, Tendering and Post Tender Negotiation, accessed 4 June 2018

Further reading