Engineering:Growian

From HandWiki
GROWIAN
Growian001.png
GROWIAN in 1984
<mapframe zoom="5" frameless="1" align="center" longitude="8.950066" latitude="53.927333" height="200" width="300">{"type":"Feature","geometry":{"coordinates":[8.950066,53.927333],"type":"Point"},"properties":{"marker-color":"#5E74F3","title":"Growian","marker-symbol":"industrial"}}</mapframe>
CountryGermany
LocationSchleswig-Holstein
Coordinates [ ⚑ ] : 53°55′38″N 8°57′00″E / 53.927333°N 8.950066°E / 53.927333; 8.950066
StatusDecommissioned
Construction began1976
Project commissioning1983
Decommission date1987
Owner(s)Growian GmbH
Operator(s)Growian GmbH
Wind farm
TypeOnshore
Hub height100 metres (330 ft)
Rotor diameter100 metres (330 ft)
Rated wind speed12 metres per second (39 ft/s)
Power generation
Nameplate capacity3 MW
Annual net output12 GWh

Growian or GROWIAN (short for German "Große Windenergieanlage" - "Large wind turbine") was a publicly funded wind turbine built in the Kaiser-Wilhelm-Koog near Marne for purposes of technology testing in the 1980s. It was a two-bladed "lee runner" (the rotor was situated on the downwind side of the tower) with a hub height of about 100 metres (330 ft).

For a long time Growian was the world's largest wind turbine. Many features of the installation were novel and had not previously been trialled at this scale. Due to manufacturing faults in the casing, the turbine could not be run at full performance, and various issues with materials and construction prevented continuous testing. Consequently, the installation was idle for the greater part of the period between the first test run on 6 July 1983 (official start of operations was 4 October 1983[1]) and end of operations in August 1987. Growian was decommissioned over the course of 1987, and dismantled in summer 1988.

Technical data

thumb|left|GROWIAN with its two wind gauge pylons Growian's power rating was 3,000 kW, at the time the highest in the world. The rotor had an oscillating nave, a diameter of 100.4 metres (329 ft), and revolved at approximately 19.5 rpm. The orientation of the two blades was regulated by a mechanical-electrical mechanism. In contrast to most modern turbines, the blades rotated on the leeward side of the tower.[2][3]

The turbine house at a height of 100 metres (330 ft) weighed 340 t, and each blade weighed 23 t.[4]

The turbine had a switching on speed of 5.4 metres per second (18 ft/s) and a rated speed of 12 metres per second (39 ft/s). It would cut out at a speed of 24 metres per second (79 ft/s) and was rated for a maximum survivable speed of 60 metres per second (200 ft/s). Projected annual energy yield at a mean wind speed of 9.3 metres per second (31 ft/s) was approximately 12 GWh.[3]

Rotor and induction generator were mechanically coupled by a gearing mechanism consisting of one spur gear and two epicyclic gears. Feed-in to the power grid was realized using a set of motor–generators that was largely identical to that later used at Umspannwerk Neuhof (de), one of the few electrical substations that allowed for electricity import from the GDR. The rotors were constructed using steel walers, and in cross section consisted of a steel core, an outer skin and fibreglass reinforcement rods.[3]

The tower and one of the rotors are on display at the Auto & Technik Museum Sinsheim.

The total cost of the installation was about 87 million Deutsche Mark.[5]

Development and outcomes

Growian rotor blade with museum logo at Auto & Technik Museum Sinsheim

Towards the end of 1976, the German Federal Ministry of Education and Research (BMFT) decided to use research contracts and expert consultation to investigate the development of large wind turbines. This decision, taken as a result of public pressure, ran contrary to the stalling efforts of the major energy providers. Contracts were awarded to MAN SE, the Institute for Aerodynamics and Gas Dynamics at the University of Stuttgart, and the University of Regensburg. In 1978 the BMFT decided to construct the world's largest wind turbine with a tower height and blade diameter of 100 m. MAN SE was chosen as main contractor, and the formation of a construction and operation company was given into the charge of the reluctant Hamburgische Electricitäts-Werke (de) (HEW). This led to the formation of the Growian GmbH on 8 January 1980, of which HEW held 46.7%, Schleswag (de) held 30.1%, and RWE held 23.2%.[5]

Overall and technical direction were the responsibility of HEW, while Schleswag dealt with commercial management. The basic contract between the partners of 3 January 1978 stipulated that after the project's conclusion, the installation was "anticipated to be dismantled and scrapped".

The partners as well as the BMFT also had political motives connected with the project. Günther Klätte, management board member of RWE, stated during a general business meeting: "We require Growian [in the general sense of large wind turbines] as a proof of failure of concept", and he noted that "the Growian is a kind of pedagogical tool to convert the anti-nuclear energy crowd to the true faith".[6] A similar statement regarding the incurred financial burdens was reported of Minister of Finance and former Minister of Research Hans Matthöfer: "We know it won't do anything for us. But we do it to demonstrate to the wind energy advocates that it doesn't work."[6] After the Green Party had derided the installation as the electricity provider's "fig leaf" on the occasion of groundbreaking in May 1981, the RWE took internal measures to make sure that publicly a position of open-mindedness towards alternative energy production was emphasized while public interest in wind energy was allayed.

Insuperable structural load and material problems occurred, not least due to the two-bladed lee runner configuration. The installation turned out to be a failure in most respects, spent substantially more time under repair than up and running, and was not even capable of sustained test operation. When it was decommissioned it had only logged a total of 420 hours in active operation.[5]

Growian is regarded as one of the largest failures in the history of wind power and was unable to fulfill any of the expectations riding on its conception. What few insights were gained found little application in wind turbine construction. Some lessons were however learned from conceptional mistakes made in its construction, e.g., the futility of trying to reach profitable installation sizes without taking intermediate steps.[5]

The point of view that multi-MW-yield wind turbines were technically and commercially infeasible gained some currency after the failure of the project, but was eventually superseded by technical progress. Beginning with the late 2000s, twenty-five years after Growian was decommissioned, installations with identical dimensions and yield (100 m rotor diameter, 3 MW net yield) were being produced in large numbers, a class of turbines that has continued to dominate the market and to push forward the mean net yield of newly installed turbines. As of 2015, substantially larger installations with yields up to 8 MW and rotor diameters of up to 170 m are present in the offshore sector. In contrast to Growian, however, these turbine types were incrementally developed from smaller installations in the 0.1 MW range.

Growian's former locations is still being used for wind power generation. In 1988, Germany's first wind farm, the Windenergiepark Westküste (de), was built on a 20 hectare section of the former test area. It initially comprised 30 smaller turbines with net yields of 10-25 kW, provided by three different wind turbine manufacturers. After being repowered twice, the wind farm today consists of four major installations with 1-2 MW yield, in addition to a test area for small wind turbines and an information center presenting the history of wind power.[7]

References

  1. "4.10.1983: Windkraftanlage in Betrieb - KalenderBlatt zum 4. Oktober". http://www.kalenderblatt.de/index.php?what=ged&autorid=1813&tag=4&monat=10&dayisset=1. 
  2. Jörn Pulczynski, Jürgen Hauschildt (1995). "Growian: Zielbildung für bedeutende Innovationsvorhaben". in Klaus Brockhoff (in German). Management von Innovationen. Planung und Durchsetzung – Erfolge und Mißerfolge. Wiesbaden: Gabler. pp. 45–54. http://www.offshore-wind.de/page/fileadmin/offshore/documents/TU-Berlin_GroWiAn.pdf. 
  3. 3.0 3.1 3.2 "Der schon historische Windenergiekonverter 'GROWIAN' - Growian technical data (in German)". http://www.heiner-doerner-windenergie.de/GROWIAN.html. 
  4. Brück, Jürgen (6 September 2007). "20 Jahre Windenergiepark Westküste". http://www.energieportal24.de/artikel_2574.htm. 
  5. 5.0 5.1 5.2 5.3 Heymann, Matthias (1995). "7.3.3 - Das Growian-Projekt" (in German). Die Geschichte der Windenergienutzung 1890–1990. Frankfurt am Main: Campus. pp. 369–382. ISBN 3-593-35278-8. 
  6. 6.0 6.1 Johansen, Anatol (13 December 1982). "Erfolg für das erste Aufwindkraftwerk der Welt". Die Welt 289: pp. 12. 
  7. "Windenergiepark Westküste". http://www.windenergiepark-westkueste.de/. 
  • Heymann, Matthias (1999). "Der Riese und der Wind: Zum schwierigen Verhältnis des RWE zur Windenergie nach 1945. 3: Das Growian-Desaster 1978–1987". in Helmut Maier (in German). Elektrizitätswirtschaft zwischen Umwelt, Technik und Politik: Aspekte aus 100 Jahren RWE-Geschichte 1898–1998. Freiberg: TU Bergakademie. pp. 217–236. ISBN 3-86012-087-5. 
  • Pulczinsky, Jörn (1991) (in German). Interorganisationales Innovationsmanagement. Eine kritische Analyse des Forschungsprojektes GROWIAN. Kiel: Vauk. ISBN 3-8175-0121-8.