Activity selection problem: Difference between revisions
imported>JMinHep (update) |
(No difference)
|
Latest revision as of 16:41, 25 October 2021
The activity selection problem is a combinatorial optimization problem concerning the selection of non-conflicting activities to perform within a given time frame, given a set of activities each marked by a start time (si) and finish time (fi). The problem is to select the maximum number of activities that can be performed by a single person or machine, assuming that a person can only work on a single activity at a time. The activity selection problem is also known as the Interval scheduling maximization problem (ISMP), which is a special type of the more general Interval Scheduling problem.
A classic application of this problem is in scheduling a room for multiple competing events, each having its own time requirements (start and end time), and many more arise within the framework of operations research.
Formal definition
Assume there exist n activities with each of them being represented by a start time si and finish time fi. Two activities i and j are said to be non-conflicting if si ≥ fj or sj ≥ fi. The activity selection problem consists in finding the maximal solution set (S) of non-conflicting activities, or more precisely there must exist no solution set S' such that |S'| > |S| in the case that multiple maximal solutions have equal sizes.
Optimal solution
The activity selection problem is notable in that using a greedy algorithm to find a solution will always result in an optimal solution. A pseudocode sketch of the iterative version of the algorithm and a proof of the optimality of its result are included below.
Algorithm
Greedy-Iterative-Activity-Selector(A, s, f): Sort A by finish times stored in f S = {A[1]} k = 1 n = A.length for i = 2 to n: if s[i] ≥ f[k]: S = S U {A[i]} k = i return S
Explanation
Line 1: This algorithm is called Greedy-Iterative-Activity-Selector, because it is first of all a greedy algorithm, and then it is iterative. There's also a recursive version of this greedy algorithm.
- [math]\displaystyle{ A }[/math] is an array containing the activities.
- [math]\displaystyle{ s }[/math] is an array containing the start times of the activities in [math]\displaystyle{ A }[/math].
- [math]\displaystyle{ f }[/math] is an array containing the finish times of the activities in [math]\displaystyle{ A }[/math].
Note that these arrays are indexed starting from 1 up to the length of the corresponding array.
Line 3: Sorts in increasing order of finish times the array of activities [math]\displaystyle{ A }[/math] by using the finish times stored in the array [math]\displaystyle{ f }[/math]. This operation can be done in [math]\displaystyle{ O(n \cdot \log n) }[/math] time, using for example merge sort, heap sort, or quick sort algorithms.
Line 4: Creates a set [math]\displaystyle{ S }[/math] to store the selected activities, and initialises it with the activity [math]\displaystyle{ A[1] }[/math] that has the earliest finish time.
Line 5: Creates a variable [math]\displaystyle{ k }[/math] that keeps track of the index of the last selected activity.
Line 9: Starts iterating from the second element of that array [math]\displaystyle{ A }[/math] up to its last element.
Lines 10,11: If the start time [math]\displaystyle{ s[i] }[/math] of the [math]\displaystyle{ ith }[/math] activity ([math]\displaystyle{ A[i] }[/math]) is greater or equal to the finish time [math]\displaystyle{ f[k] }[/math] of the last selected activity ([math]\displaystyle{ A[k] }[/math]), then [math]\displaystyle{ A[i] }[/math] is compatible to the selected activities in the set [math]\displaystyle{ S }[/math], and thus it can be added to [math]\displaystyle{ S }[/math].
Line 12: The index of the last selected activity is updated to the just added activity [math]\displaystyle{ A[i] }[/math].
Proof of optimality
Let [math]\displaystyle{ S = \{1, 2, \ldots , n\} }[/math] be the set of activities ordered by finish time. Assume that [math]\displaystyle{ A\subseteq S }[/math] is an optimal solution, also ordered by finish time; and that the index of the first activity in A is [math]\displaystyle{ k\neq 1 }[/math], i.e., this optimal solution does not start with the greedy choice. We will show that [math]\displaystyle{ B = (A \setminus \{k\}) \cup \{1\} }[/math], which begins with the greedy choice (activity 1), is another optimal solution. Since [math]\displaystyle{ f_1 \leq f_k }[/math], and the activities in A are disjoint by definition, the activities in B are also disjoint. Since B has the same number of activities as A, that is, [math]\displaystyle{ |A| = |B| }[/math], B is also optimal.
Once the greedy choice is made, the problem reduces to finding an optimal solution for the subproblem. If A is an optimal solution to the original problem S containing the greedy choice, then [math]\displaystyle{ A^\prime = A \setminus \{1\} }[/math] is an optimal solution to the activity-selection problem [math]\displaystyle{ S' = \{i \in S: s_i \geq f_1\} }[/math].
Why? If this were not the case, pick a solution B′ to S′ with more activities than A′ containing the greedy choice for S′. Then, adding 1 to B′ would yield a feasible solution B to S with more activities than A, contradicting the optimality.
Weighted activity selection problem
The generalized version of the activity selection problem involves selecting an optimal set of non-overlapping activities such that the total weight is maximized. Unlike the unweighted version, there is no greedy solution to the weighted activity selection problem. However, a dynamic programming solution can readily be formed using the following approach:[1]
Consider an optimal solution containing activity k. We now have non-overlapping activities on the left and right of k. We can recursively find solutions for these two sets because of optimal sub-structure. As we don't know k, we can try each of the activities. This approach leads to an [math]\displaystyle{ O(n^3) }[/math] solution. This can be optimized further considering that for each set of activities in [math]\displaystyle{ (i, j) }[/math], we can find the optimal solution if we had known the solution for [math]\displaystyle{ (i, t) }[/math], where t is the last non-overlapping interval with j in [math]\displaystyle{ (i, j) }[/math]. This yields an [math]\displaystyle{ O(n^2) }[/math] solution. This can be further optimized considering the fact that we do not need to consider all ranges [math]\displaystyle{ (i, j) }[/math] but instead just [math]\displaystyle{ (1, j) }[/math]. The following algorithm thus yields an [math]\displaystyle{ O(n \log n) }[/math] solution:
Weighted-Activity-Selection(S): // S = list of activities sort S by finish time opt[0] = 0 // opt[j] represents optimal solution (sum of weights of selected activities) for S[1,2..,j] for i = 1 to n: t = binary search to find activity with finish time <= start time for i // if there are more than one such activities, choose the one with last finish time opt[i] = MAX(opt[i-1], opt[t] + w(i)) return opt[n]
References
External links
Original source: https://en.wikipedia.org/wiki/Activity selection problem.