Engineering:Prototype Fast Breeder Reactor
PFBR | |
---|---|
Generation | Generation IV reactor |
Reactor concept | Sodium-cooled fast reactor |
Reactor line | IFBR |
Designed by | IGCAR |
Manufactured by | BHAVINI |
Status | Under development |
Main parameters of the reactor core | |
Fuel (fissile material) | 235U/239Pu (NEU/239Pu/MOX) |
Fuel state | Solid |
Neutron energy spectrum | Fast |
Primary control method | control rods |
Primary coolant | Liquid Sodium |
Reactor usage | |
Primary use | Breeding of 233U for AHWR-300 and Generation of electricity |
Power (thermal) | 1253 |
Power (electric) | 500 |
Prototype Fast Breeder Reactor | |
---|---|
<mapframe zoom="5" frameless="1" align="center" longitude="80.173333333333" latitude="12.553055555556" height="200" width="300">{"type":"Feature","geometry":{"coordinates":[80.17333333333333,12.553055555555556],"type":"Point"},"properties":{"marker-color":"#5E74F3","title":"Prototype Fast Breeder Reactor","marker-symbol":"industrial"}}</mapframe> | |
Country | India |
Location | Madras |
Coordinates | [ ⚑ ] : 12°33′11″N 80°10′24″E / 12.55306°N 80.17333°E |
Status | Under construction |
Construction began | 2004 |
Project commissioning | October 2022 (planned)[1] |
Construction cost | ₹5,850 crore (equivalent to ₹170 billion or US$2.43 billion in 2019)[1] |
Owner(s) | BHAVINI |
Operator(s) | BHAVINI |
Nuclear power station | |
Reactor type | fast breeder |
Power generation | |
Nameplate capacity | 500 MW |
The Prototype Fast Breeder Reactor (PFBR) is a 500 MWe fast breeder nuclear reactor presently being constructed at Kokkilamedu, near Kalpakkam, in Tamil Nadu state, India .[2] The Indira Gandhi Centre for Atomic Research (IGCAR) is responsible for the design of this reactor. The facility builds on the decades of experience gained from operating the lower power Fast Breeder Test Reactor (FBTR). At first, the reactor's construction was supposed to be completed in September 2010, but there were several delays. The Prototype Fast Breeder Reactor is scheduled to be put into service in December 2024, which is more than 20 years after construction began and 14 years after the original commissioning date, as of December 2023. The project's cost has doubled from ₹3,500 crore to ₹7,700 crore due to the multiple delays. The project currently holds an infamous record of being the longest under-construction nuclear reactor project in the world.[3][4]
Background
The Kalpakkam PFBR is designed to use uranium-238 to breed plutonium in a sodium-cooled fast reactor design. The surplus plutonium (or uranium-233 for thorium reactors) from each fast reactor can be used to set up more such reactors and grow the nuclear capacity in tune with India's needs for power. The PFBR is a part of the three-stage nuclear power program.
India has the capability to use thorium cycle based processes to extract nuclear fuel. This is of special significance to the Indian nuclear power generation strategy as India has one of the world's largest reserves of thorium, which could provide power for more than 10,000 years,[5] and perhaps as long as 60,000 years.[6][7]
History
The design of this reactor was started in the 1980s, as a prototype for a 600 MW FBR. Construction of the first two FBR are planned at Kalpakkam, after a year of successful operation of the PFBR. Other four FBR are planned to follow beyond 2030, at sites to be defined.[8]
In 2007, the reactor was planned to begin its operation in 2010, but as of 2019, it was expected to reach first criticality in 2020.[9] The power island of this project was engineered by Bharat Heavy Electricals Limited (BHEL), largest power equipment utility of India.[citation needed]
In July 2017, it was reported that the reactor is in final preparation to go critical.[10] However in August 2020, it was reported that the reactor might go critical only in December 2021.[11]
As of February 2021, around ₹6,840 crore (US$958.97 million) have been spent in the construction and commissioning of the reactor. The reactor is now expected to be operational by October 2022.[1][12]
Technical details
The reactor is a pool type LMFBR with 1,750 tonnes of sodium as coolant. Designed to generate 500 MWe of electrical power, with an operational life of 40 years, it will burn a mixed uranium-plutonium MOX fuel, a mixture of PuO2 and UO2. A fuel burnup of 100 GWd/t is expected. The Fuel Fabrication Facility (FFF), under the direction of Bhabha Atomic Research Centre (BARC), Tarapur is responsible for the fuel rods manufacturing. FFF comes under "Nuclear Recycle Board" of Bhabha Atomic Research Center and has been responsible for fuel rod manufacturing of various types in the past.[citation needed] FFF Tarapur in early 2023 had successfully completed fabrication of 100,000 PFBR fuel elements[clarification needed].[13]
Safety considerations
The prototype fast breeder reactor has a negative void coefficient, thus ensuring a high level of passive nuclear safety. This means that when the reactor overheats (below the boiling point of sodium) the speed of the fission chain reaction decreases, lowering the power level and the temperature.[14] Similarly, before such a potential positive void condition may form from a complete loss of coolant accident, sufficient coolant flow rates are made possible by the use of conventional pump inertia, alongside multiple inlet-perforations, to prevent the possible accident scenario of a single blockage halting coolant flow.[15]
The active-safety reactor decay heat removal system consists of four independent coolant circuits of 8MWt capacity each.[16] Further active defenses against the positive feedback possibility include two independent SCRAM shutdown systems, designed to shut the fission reactions down effectively within a second, with the remaining decay heat then needing to be cooled for a number of hours by the 4 independent circuits.
The fact that the PFBR is cooled by liquid sodium creates additional safety requirements to isolate the coolant from the environment, especially in a loss of coolant accident scenario, since sodium explodes if it comes into contact with water and burns when in contact with air. This latter event occurred in the Monju reactor in Japan in 1995, although sodium burns only gently in air, and the sodium leak did not release any radioactive elements. Another consideration with the use of sodium as a coolant is the absorption of neutrons to generate the radioactive isotope 24Na, which has a 15-hour half life.[17]
See also
- FBR-600 Commercial variant of the PFBR design
- India's three stage nuclear power programme
References
- ↑ 1.0 1.1 1.2 "Lok Sabha Unstarred Question No. 330, Budget Session 2021". Department of Atomic Energy, Government of India. 3 February 2021. https://dae.gov.in/writereaddata/lsusq%20330.pdf.
- ↑ Baldev Raj, S.C. Chetal and P. Chellapandi (8 January 2010). "Great expectations". Nuclear Engineering International. http://www.neimagazine.com/story.asp?storyCode=2055120.
- ↑ Laxman, Srinivas (2023-12-16). "15 years on, US nuke deal waits for power plug". The Times of India. ISSN 0971-8257. https://timesofindia.indiatimes.com/india/15-years-on-us-nuke-deal-waits-for-power-plug/articleshow/106048796.cms?from=mdr.
- ↑ "India gives update on nuclear construction projects : New Nuclear - World Nuclear News". https://www.world-nuclear-news.org/Articles/India-gives-update-on-nuclear-construction-project.
- ↑ Chris Rhodes (26 February 2012). "Thorium can power civilization for over 3000 years". http://ergobalance.blogspot.in/2012/02/thorium-age-is-not-here-yet.html.
- ↑ MacKay, David J. C. (20 February 2009). Sustainable Energy - Without the Hot Air. UIT Cambridge Ltd.. p. 166. http://www.inference.phy.cam.ac.uk/withouthotair/c24/page_166.shtml. Retrieved 2012-03-23.
- ↑ Rodricks, Dan (9 May 2011). "Thor's nuclear-powered hammer". The Baltimore Sun. http://articles.baltimoresun.com/2011-05-09/news/bs-ed-rodricks-thorium-20110509_1_thorium-nuclear-renaissance-nuclear-expansion.
- ↑ "India plans to construct six more fast breeder reactors". The Economic Times. 1 December 2015. http://articles.economictimes.indiatimes.com/2015-12-01/news/68688445_1_fuel-loading-prototype-fast-breeder-reactor-pfbr.
- ↑ "Prototype Fast Breeder Reactor at Kalpakkam in integrated commissioning stage". THEWEEK. 15 December 2021. https://www.theweek.in/wire-updates/national/2021/12/15/del31-lsq-atomic-kalpakkam-plant.html.
- ↑ "Nuclear reactor at Kalpakkam: World's envy, India's pride". The Times of India. 2017-11-26. https://timesofindia.indiatimes.com/india/nuclear-reactor-at-kalpakkam-worlds-envy-indias-pride/articleshow/59407602.cms.
- ↑ "India's First Prototype Fast Breeder Reactor Has a New Deadline. Should We Trust It?". https://science.thewire.in/the-sciences/prototype-fast-breeder-reactor-dae-bhavini-npcil-liquid-sodium-coolant-purchase-orders/.
- ↑ "Prototype Fast Breeder Reactor at Kalpakkam in integrated commissioning stage". https://www.theweek.in/wire-updates/national/2021/12/15/del31-lsq-atomic-kalpakkam-plant.html.
- ↑ Republic Day Address, BARC Director.
- ↑ Raj, Baldev (30 October 2009). "Design Robustness and Safety Adequacy of India's Fast Breeder Reactor". Science & Global Security 17 (2–3): 194–196. doi:10.1080/08929880903451397. Bibcode: 2009S&GS...17..194R.
- ↑ Raj, Baldev (30 October 2009). "Design Robustness and Safety Adequacy of India's Fast Breeder Reactor". Science & Global Security 17 (2–3): 194–196. doi:10.1080/08929880903451397. Bibcode: 2009S&GS...17..194R.
- ↑ "Design of 500 MWe Prototype Fast Breeder Reactor". http://www.dae.gov.in/ni/nimar04/design.pdf.
- ↑ Busse, J.G. (April 1978). "Slow breeder makes its own nuclear fuel". Popular Science 212 (4): pp. 89–91, 200, 202. https://books.google.com/books?id=tQAAAAAAMBAJ&pg=PA89.
External links
- "Kalpakkam PFBR to be completed ahead of schedule; 4 more to come up by 2020". The Hindu. 7 September 2005. http://www.hinduonnet.com/2005/09/07/stories/2005090704781300.htm.
- The design of the Prototype Fast Breeder Reactor, Nuclear Engineering and Design, April 2006
Original source: https://en.wikipedia.org/wiki/Prototype Fast Breeder Reactor.
Read more |